1,350 m3/d Pickling Wastewater Metals & Hardness Removal

Separate reaction solids after conditioning and provide an interface for reuse or downstream treatment.

Project scale
1,350 m³/d
Feed / process stream
Steel pickling wastewater
Membrane sections
Chemical conditioning + metals/hardness precipitation + tubular membrane separation
1,350 m3/d steel pickling wastewater tubular membrane system
Project-related system image. Customer identity and operating-performance data are not published.

01 · Engineering task

What the project needed to resolve

Separate reaction solids after conditioning and provide an interface for reuse or downstream treatment.

02 · Membrane sections

The documented membrane process route

Chemical conditioning + metals/hardness precipitation + tubular membrane separation

Configuration, operating windows, and guarantees are not transferred automatically to a new duty.

03 · Plum scope

Only the confirmed participation boundary is stated

This page records only the confirmed membrane sections. Reagent programs, upstream and downstream units, utilities, terminal streams, and whole-plant performance remain subject to project documents.

04 · Public project facts

Facts available for preliminary comparison

Published facts include a project scale of 1,350 m³/d, the feed or process stream “Steel pickling wastewater”, and the membrane route “Chemical conditioning + metals/hardness precipitation + tubular membrane separation”. Customer identity and operating-performance data are not published.