Industrial Wastewater Reuse & ZLD
400 m3/d Landfill Leachate Ammonia Stripping Validation
Reduce front-end ammonia loading and define gas, liquid, absorption, and downstream biological interfaces.

01 · Engineering task
What the project needed to resolve
Reduce front-end ammonia loading and define gas, liquid, absorption, and downstream biological interfaces.
02 · Membrane sections
The documented membrane process route
Preheat/desorption + ammonia stripping + absorption/downstream biology interface
Configuration, operating windows, and guarantees are not transferred automatically to a new duty.
03 · Plum scope
Only the confirmed participation boundary is stated
This page records only the confirmed membrane sections. Reagent programs, upstream and downstream units, utilities, terminal streams, and whole-plant performance remain subject to project documents.
04 · Public project facts
Facts available for preliminary comparison
Published facts include a project scale of 400 m³/d, the feed or process stream “Aged landfill leachate”, and the membrane route “Preheat/desorption + ammonia stripping + absorption/downstream biology interface”. Customer identity and operating-performance data are not published.